|
From the editors of Wolters Kluwer Law & Business, this update describes
important developments from CCH energy publications.
If you have any comments or suggestions concerning
the information provided or the format used, we'd like to hear from you.
Please send your comments to pamela.maloney@wolterskluwer
Nuclear Power
NRC Receives First Nuclear Power Plant
Application in 29 Years
NRG Energy, Inc. and South Texas
Project Nuclear Operating Company have announced that they are filing
an application with the Nuclear Regulatory Commission (NRC) to build and
operate two new nuclear units at the South Texas Project nuclear power
station site. This marks the first nuclear power plant start application
in 29 years. The total rated capacity of the new units, which are expected
to come on-line in 2014 and 2015, respectively, will equal or exceed 2,700
megawatts. David Crane, NRG’s President and Chief Executive Officer,
said advanced nuclear technology is the only currently viable large-scale
alternative to traditional coal-fueled generation that will produce none
of the traditional air emissions, notably carbon dioxide and other greenhouse
gases. (CCH Nuclear Regulation Reporter, No. 1378, October 9,
2007)
Assessment of Aircraft Impact on New
Reactor Designs Proposed
Applicants for new reactor design
certification would be required to assess the effects of the crash of
a large commercial aircraft on their nuclear power plant under the provisions
of a new NRC proposal. On the basis of these assessments, applications
would include a description and evaluation of design features, functional
capabilities, and strategies to avoid or mitigate, as much as possible,
the effects of the crash of the aircraft, with reduced reliance on operator
actions. The applications would have to address core cooling capability,
containment integrity, and spent fuel pool integrity, all of which could
be compromised by the large fires and explosions that would likely result
from the plane’s impact. The impact of a large aircraft is a beyond-design
–basis event and the NRC’s requirements applicable to the
construction, testing and operation of design features, functional capabilities
and strategies for design basis events would not be applicable to design
features functional capabilities or strategies selected by the applicant
solely to meet the requirements of this rule. (CCH Nuclear Regulation
Reporter ¶4232)
Utility Entitled to $116 Million for
DOE’s Failure to Accept SNF
A utility was entitled to damages
totaling more than $116 million because of the Department of Energy’s
(DOE) failure to accept the utility’s spent nuclear fuel (SNF) and
high level radioactive waste on a timely basis. The federal government,
which had a long established responsibility for the disposal of these
wastes, partially breached a 1983 contract that it signed with the utility
in which the government agreed to dispose of the company’s SNF beginning
no later than January 31, 1998. Although the U.S. argued that many of
the costs would have been incurred regardless of DOE’s delay, the
utility demonstrated that it had incurred substantial and foreseeable
costs in mitigating DOE’s acknowledged, impending and substantial
delay in the performance of its contractual obligations and that the delay
was a substantial causal factor in its expenditure decisions. As a result,
the utility was entitled to mitigation costs it incurred, largely through
the off-site storage of spent fuel and the construction of a dry cask
storage facility. Both of these decisions were reasonable and their costs
were demonstrated with reasonable certainty. (Northern States Power
Co. v. U.S. (ClCt) CCH Nuclear Regulation Reporter ¶20,678)
Electric Utilities
Commission Institutes Settlement Procedures
for PJM
In a case concerning two complaints
filed against PJM Interconnection, L.L.C. (PJM), alleging tariff violations
and interference with the independence of PJM’s Market Monitor,
the Commission found that PJM had not committed tariff violations and
that the existing record was sufficient to support that finding. The Commission
further found that the significant tension between PJM management and
the Market Monitor could compromise the market monitoring unit’s
(MMU) ability to perform its tariff-defined functions, requiring tariff
modifications to reform that relationship. The complaints had been filed
by a group of states, municipalities and cooperatives, and by the Organization
of PJM States, Inc. (Allegheny Electric Cooperative, Inc., et al.
v. PJM Interconnection, L.L.C., et al. 120
FERC ¶61,254 (ip
access user)).
Entergy Ordered to Make Compliance
Filing/Refunds
Consistent with an order of
remand from the U.S. Court of Appeals for the District of Columbia Circuit
[CCH Utilities Law Reports ¶14,648; see summary in Opinions, Orders
and Decisions Report Letter 1357, July 25, 2007], the Commission directed
Entergy Corporation (Entergy) to file a compliance filing that recalculated
customers’ peak load responsibility to remove interruptible load
from the computation of charges for the Entergy system since April 1,
2004. Entergy was also ordered to make refunds to Entergy’s Louisiana
customers reflecting the difference between what Entergy charged, based
on Opinion Nos. 468 [106
FERC ¶61,228 (ip
access user)] and 468-A [111
FERC ¶61,080 (ip
access user)], and what it would have charged had Entergy at that
time immediately removed all interruptible load from the computation of
peak load responsibility (Louisiana Public Service Commission, et
al. v. Entergy Corporation, 120
FERC ¶61,241 (ip
access user)).
Pipeline Proxy Group Issue Remanded,
Risk Explanation Required
The Federal Energy Regulatory
Commission (FERC) erred in its selection of ``proxy groups'' used to calculate
the gas transmission rates for two natural gas pipeline companies, and
in its placement of the companies within those proxy groups, by failing
to explain how its proxy group arrangements were based on the principle
of relative risk, the U.S. Court of Appeals for the District of Columbia
Circuit held. The court determined that there was no adequate support
in the record for the contention that FERC's proxy group arrangements
were risk-appropriate. In its ruling for one of the pipeline companies,
the court said that, while FERC stated that changes in the gas pipeline
industry compelled a new approach to proxy groups, nothing in FERC's explanation
stated why the companies selected were risk-comparable to the pipeline
company.
The court also addressed matters relating to
the settlement agreement between one of the pipeline companies and gas
shippers pertaining to shipping rates, ruling that FERC's rejection of
the settlement agreement was neither arbitrary nor capricious. In addition,
the court held that FERC's selection of a faster depreciation rate for
the pipeline company's system was neither arbitrary nor capricious and
was well within the considerable deference a court shows the agency in
ratemaking cases. Finally, the court ruled that FERC's modification of
its own formula that it used to determine the pipeline company's management
fee was neither arbitrary nor capricious. FERC was not required to choose
the best solution, only a reasonable one, and the pipeline company provided
no evidence that FERC's approach was unreasonable, according to the court.
(Petal Gas Storage, L.L.C. v. FERC (DCCir), CCH Utilities
Law Reporter ¶14,665)
Court Upholds Terms of MISO's Tariff
Federal Energy Regulatory Commission
(FERC) orders accepting the Midwest Independent System Operator's (MISO)
proposed tariff under which MISO administers two competitive wholesale
power markets—a day-ahead market that allows transmission to be
scheduled in advance, and a real-time or ``spot'' market—were upheld
by the U.S. Court of Appeals for the District of Columbia. Among its conclusions,
the court found that FERC reasonably refused to direct MISO to use a market
concentration measure to define narrow constrained areas (NCAs) under
the ISO's proposed new tariff. The court also upheld FERC's conclusion
that a fixed cost adder under MISO's new tariff was necessary ``to provide
an efficient incentive to invest,'' stating that FERC's was a reasonable
judgment about the future behavior of entities that FERC regulates. (Wisconsin
Public Power Inc. v. FERC (DCCir), CCH Utilities Law Reporter ¶14,661)
PUC Could Not Rescind Portion of Long-Term
QF Rate Schedule
The New Hampshire Public Utility
Commission (PUC) could not rescind the final 10 years of a 30-year rate
schedule applicable to three small qualifying hydroelectric facilities
(QFs) because federal law preempted the field of rate regulation with
respect to these generating facilities and precluded the PUC from modifying
the rates initially set, the U.S. District Court for the District of New
Hampshire held. Federal Energy Regulatory Commission (FERC) regulations,
developed to implement the Public Utility Regulatory Policies Act (PURPA),
require public utilities to purchase electricity from qualifying facilities
at a rate equal to the utility's avoided cost unless the state PUC initially
determined that a lower rate is in the public interest. Although the New
Hampshire PUC argued that the rate schedule for the final 10 years of
the arrangement it had with the QFs were not just and reasonable, FERC
regulations specify that a QF has the right to receive the benefit of
its long-term rate schedule even if, due to changed circumstances or faulty
predictions of the utility's future avoided costs, the price at which
the utility is obligated to purchase electricity at the time of delivery
is unfavorable to the utility. (Greenwood v. New Hampshire Public
Utilities Comm'n (DNH), CCH Utilities Law Reporter ¶14,662)
Natural Gas
Coverage Expanded for Blanket Certificate
Abandonments
The Federal Energy Regulatory
Commission has further expanded the scope of blanket certificate eligibility
for natural gas pipelines. The Commission determined that its standard
regulations for the abandonment of natural gas facilities under blanket
certificate authority precluded abandonment of facilities built before
1982, the year that the blanket certificate program began. Previously,
facilities were built on a case-specific basis. As a result, instead of
restricting blanket certificate abandonments to facilities constructed
after 1982 and comparing a facility’s original cost to the cost
cap in effect at the time the facility was placed in service, companies
will be required to compare the estimated current cost to replicate their
existing facility using the current per-project cost cap. If the estimated
current cost to replicate the facility would not exceed the currently
effective project cost cap, the company will be permitted to employ blanket
certificate authority to abandon a facility built under case-specific
authority, provided that the existing facility could qualify for authorization
under the current blanket program. (CCH FERC Statutes and Regulations
Edition ¶19,646
(ip
access user); ¶31,255
(ip
access user))
Commission Authorizes Calhoun LNG Project
Calhoun LNG, L.P. (Calhoun)
was granted authority to site, construct, and operate a liquefied natural
gas (LNG) import terminal and associated facilities at the Port of Port
Lavaca-Point Comfort in Calhoun County, Texas. Authorization was given
to Point Comfort Pipeline Company, L.P. (Point Comfort) to construct and
operate a pipeline, the Point Comfort Pipeline, from the tailgate of Calhoun’s
proposed LNG terminal to various interstate and intrastate pipelines (Calhoun
LNG, L.P., et al. 120
FERC ¶61,259 (ip
access user)).
SESH/Southern Transmission Facilities
Approved
Upon completion of its analysis
of a proposed project by Southeast Supply Header, LLC (SESH) and Southern
Natural Gas Company (Southern), the Commission has granted the requested
authorizations, subject to certain conditions. SESH and Southern have
proposed the construction and operation of 269 miles of new natural gas
transmission facilities beginning near the Perryville Hub in Louisiana,
continuing through Mississippi, and terminating in Alabama. The first
104.1 miles would consist of 42-inch diameter pipeline, and the remainder
would consist of 164.9 miles of 36-inch diameter pipeline (Southeast
Supply Header, LLC, et al,. 120
FERC ¶61,257 (ip
access user)).
Complete Rewrite of MMS Pipeline Regulations
Proposed
The Minerals Management Service
has issued a proposed rule that would rewrite MMS regulations on pipelines
and pipeline rights-of-way (ROW) in the Outer Continental Shelf. MMS stated
that the purpose of the proposed rule is to bring the regulations up to
date by incorporating new and revised industry standards into the regulations,
along with several Notices to Lessees and Operators (NTLs) and a Letter
to Lessees and Operators (LTL) that were issued since the regulations
were last significantly updated in 1998. The regulations have also been
rewritten in plain language. These regulations are generally located in
Subpart J of Part 250 of the regulations. The rules would apply to all
lessees, designated lease operators, and pipeline ROW holders operating
in the OCS. Comments are due by January 31, 2008. (CCH Energy Management
¶9314)
|