|
From the editors of Wolters Kluwer Law & Business, this update describes
important developments from CCH energy publications.
If you have any comments or suggestions concerning
the information provided or the format used, we'd like to hear from you.
Please send your comments to pamela.maloney@wolterskluwer
FERC Daily Document Update/Customized Tracker Launched
The Federal Energy Guidelines tab now includes
a Daily Document Update Service which is designed to provide access to
all materials released each day and designated as final by FERC. These
documents include: rulemakings, decisions, opinions, Office Director Orders,
and decisions by Administrative Law Judges. This DDU includes a customizable
tracker to help our subscribers keep up-to-date with the key energy issues
and developments. Our subscribers receive an e-mail every time documents
are posted or they can customize their tracker to receive an e-mail only
when documents are posted on selected topics. The topics include: Electric
Utilities, Natural Gas, Hydroelectric Power, Oil Pipelines, Crude Oil,
Critical Energy Infrastructure Information, Rulemakings, Policy Statements
and Accounting Issues.
Nuclear Power
Lower NRC Inspection and Licensing
Fees Proposed for 2008
Generally lower licensing and
inspection fees for applicants and licensees have been proposed by the
Nuclear Regulatory Commission for 2008. NRC is required to recover almost
all of its budget authority (90 percent this year)—minus the $29
million appropriated from the Nuclear Waste Fund for high-level waste
activities. The total amount to be recovered for fiscal year 2008--$779.1
million—is approximately $110 million more than last year. The two
professional hourly rates previously charged by the agency for licensing
and inspection services would again be replaced with one hourly rate of
$238 for activities in both the nuclear reactor safety program and the
nuclear materials and waste safety program. This represents a 7.7 percent
decrease from the 2007 hourly rate of $258 per hour. While most annual
fees would be lower for 2008, most power reactor licensees would have
to pay $4,237,000 in annual fees, up from last year’s $4,043.000.
(CCH Nuclear Regulation Reporter ¶4234.)
Utility Entitled to $40 Million for
Diminished Plant Value
A utility was entitled to damages
totaling more than $40 million because the Department of Energy’s
(DOE) failure to accept the utility’s spent nuclear fuel on a timely
basis diminished the value of the nuclear plant the utility was selling,
the U.S. Court of Federal Claims has ruled. The federal government has
a long-established responsibility for the permanent disposal of SNF and
was obligated by contract to begin disposing of it by January 31, 1998.
According to the court, the utility demonstrated that it had incurred
substantial and foreseeable costs in mitigating DOE’s acknowledged
delay and that the delay was a substantial causal factor both in its respective
expenditure decisions and in the diminished value of the plant due to
the need for continued SNF storage. As a result, the utility, which retained
its claims relating to DOE’s contract default, was entitled to $40,030,000
in storage costs that it included in the decommissioning trust fund that
it provided to the purchaser. (Boston Edison Co., et al. v. U.S.
(Fed.Cls.) CCH Nuclear Regulation Reporter ¶20,682)
Electric Utilities
Improved Operations for Wholesale Power
Markets Proposed
New rules to improve operations
in organized electric markets, boost competition and bring additional
benefits to consumers have been proposed by the Federal Energy Regulatory
Commission. The proposed reforms are designed to ensure just and reasonable
rates, to remedy undue discrimination and preference, and to improve wholesale
competition in organized markets. They address demand response and market
pricing during a period of reserve shortage, long-term power contracting,
improved market monitoring, and the responsiveness of regional transmission
operators and independent system operators to stakeholders and customers.
(CCH Federal Energy Regulatory Commission Reporter, Statutes and
Regulations Edition ¶32,627
(ip
access user))
Stronger Cross-Subsidization Safeguards
Approved
Restrictions on affiliate transactions
between franchised public utilities that have captive customers or that
own or provide transmission service over jurisdictional transmission facilities
and their market-regulated power sales affiliates or non-utility affiliates
have been codified by FERC. The new rule expands the transactions and
entities to which these restrictions apply in order to protect against
inappropriate cross-subsidization of market-regulated and unregulated
activities by the captive customers of public utilities. Specifically,
the uniform affiliate restrictions require the Commission’s approval
of all power sales by a franchised utility with captive customers to a
market-regulated power sales affiliate and requires a franchised utility
with captive customers to provide non-power goods and services to a market-regulated
power sales affiliate at a price that is the higher of cost or market
price (CCH Federal Energy Regulatory Commission Reporter, Statutes
and Regulations Edition ¶31,264
(ip
access user))
FERC's Rejection of Old Dominion's
Rate Filing Upheld
An electric cooperative's contention
that certain of its transmission facilities were network upgrades under
a regional transmission organization's (RTO) tariff was properly rejected
by the Federal Energy Regulatory Commission (FERC), the United States
Court of Appeals for the District of Columbia Circuit held. Old Dominion
Electric Cooperative, Inc. claimed that the PJM Interconnection L.L.C.
Open Access Transmission Tariff (Tariff) did not apply to its rate filing
because the facilities—1,800 feet of transmission line and a substation—could
not be both transmission facilities and classified as network upgrades.
The court found that FERC “sensibly” rejected Old Dominion's
either/or contention when it determined that network upgrades also could
serve as transmission facilities and noted that the Tariff made “no
distinction … between network upgrades and transmission facilities.”
Also, FERC was reasonable in its findings that the lack of designation
of the facilities as network upgrades in the transmission owners' agreement
(TOA) or the Tariff, or any other part of the record, was irrelevant.
The only reason for designating the facilities as such would be to ensure
that the cooperative “repay” another entity for the cost of
constructing the facilities. However, the court said, there was no reason
to designate Old Dominion's facilities as network upgrades when the cooperative
already was paying for the construction costs itself. In addition, the
court held that there was insufficient evidence in the record to support
the contention that FERC’s determination that the Tariff precluded
Old Dominion from recovering the cost of building the cooperative's interconnection
facilities through transmission revenue was unduly discriminatory. (Old
Dominion Electric Coop., Inc. v. FERC (DCCir) CCH Utilities
Law Reporter ¶14,685)
Cross-Border Facilities Cost Allocation
Plan Accepted
A compliance filing on fixed
cost recovery policies for pricing transmission service between the Midwest
Independent Transmission System Operator, Inc. (Midwest ISO) and PJM Interconnection,
L.L.C. (PJM) was accepted by the Federal Energy Regulatory Commission
(FERC). FERC also rejected a complaint by American Electric Power Service
Corporation (AEP) that challenged those policies. FERC had directed Midwest
ISO and PJM, two broad multi-state regional transmission organizations
(RTOs), to provide in a compliance filing more detail on their joint RTO
planning model and to make use of the model transparent to their stakeholders
and to FERC. The RTOs filed an Independent RTO Pricing Design (IRPD) proposal
that would continue to use their existing inter-RTO rate design—a
license-plate/zonal rate design—to price transmission service between
the RTOs to take effect Feb. 1, 2008. AEP's complaint challenged the justness
and reasonableness of the rate design and cost allocation methodology
under the RTOs’ tariffs, and, alternatively, advocated a postage-stamp
rate design for all new and existing high-voltage facilities across the
combined Midwest ISO/PJM region. However, FERC could not find that the
rate design under the Midwest ISO and PJM tariffs was unjust, unreasonable,
or unduly discriminatory, nor that imposition of a postage-stamp rate
design across the combined Midwest ISO/PJM region was required. Further,
FERC determined that changing the license-plate rate design would produce
significant cost shifts, which FERC said could pose potential risk to
RTO membership. (American Electric Power Service Corp. v. Midwest
Independent Transmission System Operator, Inc., et al., 122
FERC ¶61,083 (ip
access user))
Cross-Border Facilities Cost Allocation
Plan Accepted
A proposal submitted by Midwest
Independent Transmission System Operator, Inc. (Midwest ISO) to establish
a mechanism for allocating the cost of new transmission facilities that
are built for reliability purposes in one Regional Transmission Organization
(RTO) but that provide benefits to another RTO (cross-border facilities)
as part of their joint operating agreement has been conditionally accepted
by the Commission as just and reasonable. Midwest ISO and the other RTO,
PJM Interconnection, LLC, (PJM) agreed to use a transfer distribution
factor (DFAX) analysis to calculate the size of each RTO's flows affecting
the constraint that a proposed cross-border facility was designed to relieve,
but could not agree on how counterflow should be netted against positive
flow in the allocation calculation. Each RTO then submitted its own proposal
on how the issue should be resolved. Midwest ISO's proposal used the total
net flow of each RTO on a constraint (all positive flow less all counterflow)
as the basis for the cost allocation between the RTOs. PJM's proposal
also considered the counterflow but only at the zonal level (Midwest
Independent Transmission System Operator, Inc., et al., 122
FERC ¶61,084 (ip
access user)).
Midwest ISO’s Market Proposal
Conditionally Accepted
A proposal by the Midwest Independent
Transmission System Operator (Midwest-ISO) to implement a day-ahead and
real-time ancillary services market has been conditionally accepted by
the Commission. Under the proposal, the Midwest ISO will determine operating
reserve requirements and procure operating reserves from all qualified
resources, in place of the current system of local management and the
procurement of reserves by the 24 balancing authorities—entities
responsible for maintaining the balance of loads and resources within
particular physical boundaries. In addition, the proposal will create
a single market for ancillary services that will allow for price competition
among resources. The proposed real-time ancillary services market provides
for greater participation by demand resources and scarcity pricing through
the use of demand curves as part of the co-optimization process, the Commission
said.(Midwest Independent Transmission System Operator, Inc.,
122
FERC ¶61,172 (ip
access user))
|