|
From the editors of Wolters Kluwer Law & Business, this update describes
important developments from CCH energy publications.
If you have any comments or suggestions concerning
the information provided or the format used, we'd like to hear from you.
Please send your comments to pamela.maloney@wolterskluwer
Legislative Action
House Passes American Clean Energy
and Security Bill
By Stephen K. Cooper, CCH Washington News Bureau
The House passed the American
Clean Energy and Security Bill of 2009 (HR 2454), a comprehensive energy
measure designed to combat global warming by capping the amount of greenhouse
gas produced by American businesses and consumers. The measure, which
passed by a vote of 219 to 212 on June 26, included few tax provisions
since House Ways and Means Chairman Charles B. Rangel, D-N.Y., decided
against convening his committee to make changes to the bill. House Minority
Leader John Boehner, R-Ohio, criticized the legislation, saying it allows
the federal government to impose new regulations and programs that will
drive up the costs of gasoline, food and electricity. This overly intrusive
energy measure would drive millions of jobs overseas to other countries
that have less strict environmental regulations, he said. Rep. Earl Blumenauer,
D-Ore., a supporter of the bill said it puts a mechanism in place to rein
in global warming and create capital that can be invested in renewable
energy sources from the wind and sun. (FERC Opinions, Orders &
Decisions, Report No. 1460, July 9, 2009)
Electric Utilities
FERC Policy Change for Electricity
Sales Reasonable, DC Circuit Finds
A decision by the Federal Energy
Regulatory Commission (FERC) to order two electricity wholesalers to make
refunds to their customers whom they had charged market-based rates in
areas where they should have charged cost-based rates was reasonable,
the U.S. Court of Appeals for the District of Columbia held. Areas served
by electricity wholesalers are divided into two categories: mitigated
areas, where a wholesaler possesses market power, and non-mitigated areas,
where the wholesaler does not. Wholesale electricity sellers are allowed
to charge market-based rates in their non-mitigated areas, but must charge
cost-based rates in their mitigated areas. In situations where the power
is sold in one region and used in another, the dispositive factor is whether
the wholesaler has market power at the point of sale, not the point of
use (``sink-based''). FERC previously used the sink-based approach, but
changed policy in 2006 to the point-of-sale approach. The court found
that: FERC thoroughly explained in a subsequently-adopted order its reasoning;
the wholesalers were not entitled to rely upon FERC's acceptance of the
sink-based test until the date it adopted its new policy; and it was reasonable
for FERC to adhere to its standard approach in declining to exercise its
authority to waive the wholesalers' refund liability. (Westar Energy
v. FERC, DCCir 2009, CCH Utilities Law Reporter
¶14,747).
Reporting Rules for New Generation
Site Acquisition Strengthened
The Commission’s market-based
rates rule has been strengthened by the agency with new reporting requirements
for the acquisition of sites for new generation capacity development.
The new requirements address wind power developers’ concerns regarding
the burden of the existing requirements as well a provide FERC with the
information necessary to evaluate a seller’s ability to erect barriers
to market entry while preserving commercially sensitive information about
future development of sites for power generating plants. Rehearing was
granted to require all entities with market-based rate authorization to
file a quarterly report detailing a seller’s acquisition of a site
for new generation capacity development for which site control has been
demonstrated in the interconnection process and for which the potential
number of megawatts that are reasonably commercially feasible on the site
for new generation capacity development is equal to 100 megawatts or more.
This replaces the previous requirement that all such sellers report these
acquisitions within 30 days. These quarterly reports must include (1)
the number of sites acquired; (2) the relevant geographic market in which
the sites are located; and (3) the maximum potential number of megawatts
that are reasonably commercially feasible on the sites reported. This
number must be justified. The information regarding the maximum potential
number of megawatts for the sites may be reported on an aggregate basis
for each relevant geographic market in which the site is located. (CCH
FERC Statutes and Regulations Edition ¶31,291
(ip
access users))
Reliability Standards for Interchange
Scheduling Updated
The approval of three updated
Interchange Scheduling and Coordination (INT) reliability standards developed
by the North American Electric Reliability Corporation (NERC): INT-005-3,
Interchange Authority Distributes Arranged Interchange; INT-006-3, Response
to Interchange Authority; and INT-008-3, Interchange Authority Distributes
Status has been proposed by the Commission. The proposed INT reliability
standards specify response time for entities in the Western Interconnection
to review and respond to requests for interchange service. Specifically,
these revisions set forth appropriate response times for all requests
for on-time, emergency, and reliability adjustment interchange service.
The proposed rule would benefit the reliable operation of the bulk power
system by clarifying how long the relevant entities have to respond to
requests for interchange service and providing entities in the Western
Interconnection with sufficient time to assess and respond to requests
for interchange service. NERC proposes to establish separate timing tables
for the Western Interconnection and the Eastern Interconnection, including
the Electric Reliability Council of Texas and Hydro-Quebec.; affirm and
clarify the increase in the reliability assessment times for the Western
Electricity Coordinating Council from five minutes to ten minutes for
requests submitted more than 60 minutes and no less than 15 minutes prior
to ramp start time; and also permit the on-time submittal of e-Tags (requests
to implement a new interchange transaction as a physical energy flow).
NERC also wants to specify the timing for responses to requests for the
Western Interconnection and modify of INT-006-002 to clarify that the
balancing authorities and transmission service providers in all Interconnections
must respond to on-time requests for interchange service, as well as to
requests for emergency and reliability adjustment interchange services.
(Revised Mandatory Reliability Standards for Interchange Scheduling
and Coordination, 127 FERC ¶61,246)
ISO-NE’s Executive Compensation
Upheld
The Attorney General for the
State of Connecticut (Connecticut AG) and the Connecticut Office of Consumer
Counsel’s (Connecticut OCC) (together, the Connecticut Parties)
requested rehearing of the Commission’s order [125 FERC ¶61,392
(ip
access users)], accepting ISO New England Inc.’s (ISO-NE) tariff
sheets for Recovery of 2009 Administrative Costs, was denied by the Commission.
The Connecticut Parties sought rehearing regarding ISO-NE’s requested
executive compensation and salary structure, employee staffing levels,
depreciation rates and schedules, and external affairs activities and
asked the Commission to hold a full evidentiary hearing to determine whether
the proposed budget would result in unjust and unreasonable rates. The
Connecticut Parties argued that the Commission erred in the order by arbitrarily,
capriciously, and without substantial evidence concluding, first, that
executive compensation package and salary level proposed by ISO-NE were
just and reasonable and, second, that the staffing and compensation levels,
depreciation and amortization schedules, and the funding for external
affairs activities proposed by ISO-NE were just and reasonable. The Commission
reaffirmed its finding in the order that ISO-NE had adequately supported
its executive compensation package, and thus it did not set the matter
for hearing. The ISO-NE provided the information in its answer necessary
to allow the Commission to determine the ISO-NE’s proposed compensation
package was just and reasonable. Regarding ISO-NE’s total staffing
and compensation to its employees, its depreciation and amortization schedules
and external affairs costs, the Commission found those were just and reasonable,
and denied rehearing on those matters as well. (ISO New England Inc.,
127 FERC ¶61,254)
Spindletop Regulatory Asset Costs for
Production Were Reasonable
An administrative law judge (ALJ) found that excluding the costs of the
Spindletop Regulatory Asset from the calculation of the Entergy Operating
Companies' (EOCs) bandwidth remedy payments was unjust, unreasonable and
unduly discriminatory. The Louisiana Public Service Commission (LPSC)
alleged in a complaint that there were errors in the methodology used
by Entergy Services, Inc. (ESI) to calculate production costs among EOCs
for purposes of determining the bandwidth remedy payments and receipts
to be made among the EOCs to maintain rough production cost equilibrium
(RPCE) on the Entergy System (System) in accord with Opinion Nos. 480
and 480-A. [111 FERC ¶61,311
(ip
access users); 113 FERC ¶61,282
(ip
access users)]. The only issue remaining for the ALJ was whether excluding
the costs of the Spindletop Regulatory Asset (SRA) from the calculation
of the EOC production cost was unjust, unreasonable and unduly discriminatory.
As a result of a ruling by the Public Utility Commission of Texas (PUCT),
Texas EOCs were subject to different treatment for Credit Payments than
the Louisiana EOCs. The consequence of the different treatments ordered
by PUCT and LPSC was that Texas customers had already paid 100 percent
of their share of capital-related costs associated with the construction
of Spindletop, while Louisiana customers had only paid a portion of their
share of those costs. Louisiana customers had the remainder of the 40-year
amortization period ordered by LPSC to pay off the balance of their share
of the SRA costs. The first question addressed by the ALJ was whether
LPSC had demonstrated that the exclusion of SRA costs from EOC Production
Costs included in the bandwidth remedy formula was unjust, unreasonable,
and unduly discriminatory, and if so, had LPSC demonstrated that the inclusion
of the costs of the SRA was just, reasonable, and not unduly discriminatory.
The ALJ found that LPSC had not proven that exclusion of SRA costs from
the bandwidth remedy formula was unjust, unreasonable, or unduly discriminatory,
nor that their remedial proposal was just, reasonable, and not unduly
discriminatory. The ALJ determined that the SRA costs were not production
costs. The SRA costs were to be distinguished from the Spindletop storage
facilities costs. The SRA was an accounting construct created by the LPSC,
that existed solely as a deferred right to recover previously incurred
costs from Louisiana retail customers. It was not a current cost of producing
electricity. (Louisiana Public Service Commission v. Entergy Corp.,
et al., 127 FERC ¶63,021)
State-by-State Potential for Demand
Response Assessed
A national assessment that estimates
the potential for demand response, both nationally and for each state,
through 2019, has been released by the Commission. The assessment, A National
Assessment of Demand Response Potential, finds the potential for peak
electricity demand reductions across the country is between 38 gigawatts
(GW) and 188 GW, up to 20 percent of national peak demand, depending on
how extensively demand response is implemented. This can reduce the need
to operate hundreds of power plants during peak times. Without any demand
response, the peak demand is estimated to grow at an annual average rate
of 1.7 percent, reaching 810 GW in 2009 and 950 GW by 2019. By reducing
electricity consumption at peak times like hot summer afternoons, when
the most expensive generators are called into service, demand response
can lower the cost of producing electricity. With full participation,
which posits the universal deployment of an advanced metering infrastructure
and the condition that dynamic pricing were made the default tariff, the
report estimates that demand response programs could reduce the projected
2019 peak load by as much as 150 GW. (CCH FERC Statutes and Regulations
Edition, Report No. 509, July 2009)
Hydroelectric Power
Lift of Stay of Deadline to Begin Hydro
Power Plant Construction Approved
A decision by the Federal Energy
Regulatory Commission (FERC) to lift a stay of a statutory deadline for
beginning construction of a hydropower plant was within FERC's discretion
because FERC's findings regarding the remaining hurdles to beginning construction
were sufficient to support the denial of an additional extension, according
to the U.S. Court of Appeals for the District of Columbia Circuit. In
1992, FERC issued Joseph Keating a license to build a hydroelectric power
plant in the Inyo National Forest in California. Keating was unable to
obtain necessary approvals from the United States Forest Service or from
the California State Water Resources Control Board. During this time,
Keating received a number of extensions from FERC, but in 2007, FERC declined
to issue another extension. FERC's conclusion that there was no reasonable
basis to expect that the licensee would be able to begin construction
in the foreseeable future was based on the fact that he had not yet received
approval of his six-year-old water rights application, had not filed and
received approval of his license amendment application, and had not filed
and received Forest Service approval of his pre-construction plans. While
Keating had litigated the issue with the Water Board, FERC was entitled
to consider the licensee's ability to obtain water rights in the immediate
future, and the court was not situated to rule on the Water Board's decision.
Furthermore, the court continued, the decision to lift the stay was within
FERC's discretion because the licensee was not entitled to an indefinite
stay. (Keating v. FERC, DCCir 2009, CCH Utilities Law Reporter
¶14,748).
Oil
Initial Decision Issued in Third Round
of Rate Challenges
In an initial decision, an administrative
law judge (ALJ) settled the third generation of complaints in a series
of proceedings challenging SFPP, L.P.'s (SFPP) system-wide rates on its
East Line and West Line filed with the Commission. The main point of disagreement
on SFPP's rates concerned the appropriate capital structure between 2000
and 2004. The ACC Shippers argued that Kinder Morgan Energy Partner's
(KMEP) capital structure should be used for SFPP, and purchase accounting
adjustments should be removed. The ALJ agreed in part finding that the
purchase accounting adjustments should be removed from the equity component
of KMEP's capital structure; however, the goodwill should remain. Additionally,
the ALJ found that the appropriate cost of debt in this proceeding is
KMEP's actual 2003 and 2004 costs of debt, including commercial paper
that KMEP classified as long-term debt, but not including special purpose
and tax-exempt bonds. SFPP met its burden of proving in the rate proceeding
that its partners incur actual or potential income tax liability on their
respective shares of the partnership income in order to prove its eligibility
for an income tax allowance. The Indicated Shippers and ACC Shippers argued
that SFPP was not entitled to an income tax allowance as a matter of law
because SFPP failed to show that its partnerships incur actual or potential
income tax liability. The ALJ found that SFPP complied with Commission
orders in calculating its income tax allowance for 2003 and 2004, and
that the KMEP incurred an actual or potential income tax liability on
the SFPP income allocated to them.
The participants in this proceeding agreed
that actual 2003 and 2004 volumes for SFPP's East and West Lines should
be used for determining just and reasonable rates. The just and reasonable
rates determined in the proceedings depend upon the final determinations
on income tax allowance, allowed return, and operation and maintenance
expenses set forth in the ALJ's decision. The airline companies involved
in these proceedings were entitled to reparations stemming from overpayments
of the West Line, while Chevron, ConocoPhillip and the Indicated Shippers
were entitled to reparations based on overpayments of rates on both lines,
according to the ALJ. Reparations are permitted when the justness and
reasonableness of existing rates is successfully challenged for shippers
that have filed complaints against a specific rate. The reparations were
to be calculated as the difference between the indexed just and reasonable
rates and the rates that the shippers actually paid, multiplied by actual
throughput, plus interest. (Chevron Products Co., et al. v. SFPP,
LP, et al., 127 FERC ¶63,024)
Safety and Environmental Management
Rule Proposed
Minerals Management Service
(MMS) proposed a rule to require operators to develop and implement a
Safety and Environmental Management System (SEMS) to address oil and gas
operations in the Outer Continental Shelf (OCS). The system would consist
of four elements: Hazards Analyses, Management of Change, Operating Procedures,
and Mechanical Integrity.The Hazards Analyses would require that a hazards
analysis (facility level) be conducted for all facilities. The Management
of Change element would require lessees/operators to document and analyze
all proposed facility changes to determine possible adverse safety and
environmental impacts, with the exception of replacement in kind. The
Operating Procedures element would require OCS oil and gas operators'
management officials to include requirements for written facility operating
procedures designed to enhance efficient, safe, and environmentally sound
operations. The Mechanical Integrity element would require that procedures
were in place to ensure that equipment was designed, fabricated, installed,
tested, inspected, monitored, and maintained in a manner consistent with
appropriate service requirements, manufacturer's recommendations, and
industry standards to promote safe and environmentally sound operations
in the OCS.The MMS believed that requiring operators to implement a Safety
and Environmental Management System would reduce the risk and number of
accidents, injuries, and spills during OCS activities. The proposed rule
explains who must have a program, what the criteria for the program are,
and what the record keeping and documentation requirements will be. For
more information see the full text of the proposed rule in CCH
Energy Management ¶9252.
Nuclear Power
NRC: Apparent Decommissioning Shortfalls
Exist
Eighteen nuclear power plants
have been asked by the Nuclear Regulatory Commission to clarify how their
owners will address the recent economic downturn’s effects on funding
to decommission their reactors in the future. Nuclear power plant operators
are required to set aside funds during a reactor’s operating life
to ensure the reactor site will be properly cleaned up once the reactor
is permanently shut down. Although this is not currently a safety issue,
the NRC’s review of the latest reports on decommissioning funding
assurance suggests several plants must adjust their funding plans to guarantee
that they are setting aside the appropriate amount of money. (CCH
Nuclear Regulation Reporter, Report No. 1419, June 30, 2009)
Higher NRC Licensing/Inspection Fees
Approved
Generally higher licensing,
inspection and annual fees for applicants and licensees have been approved
by the Nuclear Regulatory Commission for 2009. NRC is required to recover
almost all of its budget authority (90 percent this year)·minus
the amounts appropriated from the Nuclear Waste Fund for high-level waste
activities. The total amount to be recovered for fiscal year 2009--$870.6
million--is approximately $91.5 million more than last year. The professional
hourly rate charged by the agency for licensing and inspection services
has been increased to $257. This represents a 7.5 percent raise from the
2008 hourly rate of $238 per hour. The increase is primarily due to the
higher 2009 budget supporting increased regulatory and infrastructure
workload for reactor license renewals, and applications from new uranium
recovery and enrichment facilities. Under the new annual fee structure,
most power reactor licensees will have to pay $4,625,000 in annual fees
for 2009, up from last year's $4,167,000. Test and research reactors licensees
will be required to pay an annual fee of $87,600, which is significantly
higher than the 2008 amount of $76,500. High-enriched uranium fuel facility
licensees will be assessed $4,691,000 instead of last year's total of
$3,007,000, while low-enriched uranium fuel fabrication facility licensees,
who manufacture fuel for nuclear power plants, will pay $1,649,000 for
2009, rather than last year's figure of $899,000. (CCH Nuclear
Regulation Reporter, Report No. 1419, June 30, 2009)
|