January 2010


From the editors of Wolters Kluwer Law & Business, this update describes important developments from CCH energy publications.

If you have any comments or suggestions concerning the information provided or the format used, we'd like to hear from you. Please send your comments to pamela.maloney@wolterskluwer



Federal Energy Regulatory Commission

Norris Confirmed as Commissioner by U.S. Senate
The U.S. Senate voted to confirm Mr. John Norris to the Commission on December 24, 2009. Mr. Norris previously served as Chief of Staff to Secretary Tom Vilsack of the U.S. Department of Agriculture. Prior to joining the USDA, Mr. Norris served as Chairman of the Iowa Utilities Board from 2005 to 2009. As a member of the National Association of Regulatory Utility Commissioners, he worked on the Electricity Committee and was Co-Chair of the 2009 National Electricity Delivery Forum. Previously, Mr. Norris also served in various positions with the Midwest Independent System Operator. (Federal Energy Regulatory Commission Reporter, No. 1486, January 7, 2010).

Enforcement Process Made More Transparent
The Commission has acted to make its energy market enforcement process more transparent to market participants and consumers. The Commission authorized the Secretary of the Commission to issue a "Staff's Preliminary Notice of Violations" after the subject of the investigation had an opportunity to respond to staff's preliminary finding letter. This would take place upon authorization of the Director of the Office of Enforcement. The order would benefit the public interest by informing the regulated community about the views of the Office of Enforcement regarding the matter, which could contribute to a better understanding of compliance obligations. The order would also increase transparency by informing consumers of matters under investigation by the Commission Office of Enforcement. Notice would not confer a right on third parties to intervene in the investigation or any other with respect to the noticed investigation. Further, the Commission formalized a process by which the Office of Enforcement would provide exculpatory evidence to subjects of its investigations and respondents in administrative enforcement proceedings. (Enforcement of Statutes, Regulations, and Orders, 129 FERC ¶61,247 (ip access users) (Intelliconnect) ; 129 FERC ¶61,248 (ip access users) (Intelliconnect))

Electric Utilities

Normal Operations Planning Reliability Standard Interpreted
In response to a request, the North American Electric Reliability Corporation (NERC) provided an interpretation of the Commission-approved Transmission Operations Reliability Standard for Normal Operation Planning, which the Commission approved. NERC clarified that each transmission operator was required to have a study in advance of each day that can be applied to the system conditions in advance and during the day, but it was not necessary to generate a unique study for each day. A transmission operator could use a study for multiple days if system conditions on those days were similar to study conditions. Further, NERC clarified that the requirements gave no mandate on a particular type of review or study, which "may be based on complex computer studies or a manual reasonability review of previously existing study results."Finally, NERC clarified that studies provided real-time and near real-time information that should be used both to determine new system operating limits (SOLs) and identify potential "exceedences" of established SOLs, based on potential or current conditions. NERC specified that if the transmission operator determined that prior studies and SOLs may be outdated, a new study had to be performed. (North American Electric Reliability Corp., 129 FERC ¶61,191) (ip access users) (Intelliconnect)

Reliability Standards for Interchange Scheduling Adopted
Three updated Interchange Scheduling and Coordination (INT) reliability standards developed by the North American Electric Reliability Corporation (NERC): INT-005-3, Interchange Authority Distributes Arranged Interchange; INT-006-3, Response to Interchange Authority; and INT-008-3, Interchange Authority Distributes Status have been adopted by the Commission. The changes provide consistency in responding to interchange requests by clarifying timing requirements for all affected entities and facilitate the reliable operation of the bulk-power system by providing Western Electricity Coordinating Council (WECC) sufficient time to assess and respond to requests for interchange service before the underlying E-tags for these expire and by clarifying the timing requirements for the affected entities. Finally, the Commission found that separating the WECC and Eastern-Interconnection/Electric Reliability Council of Texas (ERCOT) requirements at the timing tables added clarity for entities operating in the WECC system. Retaining the slightly modified version of the prior timing tables for the sale of Eastern Interconnection and ERCOT helped to ensure consistency in responding to interchange requests in those areas as well. (Revised Mandatory Reliability Standards for Interchange Scheduling and Coordination, Order No. 730, 129 FERC ¶61,223) (ip access users) (Intelliconnect)

Need for Demand Response in Electric Markets Reaffirmed
The Commission has reaffirmed that demand response during periods of operating reserve shortages directly affects rates in wholesale electric markets and, therefore, removing barriers to demand response is consistent with FERC's duty to ensure the sound operation of those markets. In an order denying rehearing of Order No. 719-A [FERC Statutes and Regulations Edition ¶31,292], the Commission ruled that its definition of aggregators of retail customers (ARCs) as entities that aggregate demand response bids is correct and that the language of Order No. 719-A does not restrict the relevant electric retail regulatory authority's ability to determine and enforce qualification for ARCs. It also refused to provide special treatment to a particular group of aggregators by exempting them from Order No. 719-A's small system provision. (Wholesale Competition in Regions with Organized Electric Markets, Order No. 719-B, 129 FERC ¶61,252) (ip access users) (Intelliconnect)

Natural Gas

Cost-of-Service Justification Calculation Clarified
An administrative law judge (ALJ) clarified SFPP, LP's (SFPP) tariff's cost-of-service (COS) justification calculation. The COS proposed rate increases for all petroleum products movements on SFPP's West Line between Watson Station Los Angeles County, California and Phoenix, Arizona. SFPP was requesting a COS justification because it had expanded its East Line and expected the volume on the West line to decrease. Not all Shippers addressed every issue, but generally each supported any position of other Shippers or Staff which would lower the proposed cost of service, or challenged the justness and reasonableness of SFPP's proposed rate increase. SFPP will need to make necessary adjustments based upon the ALJ's findings that purchase accounting adjustments should be excluded from calculations pertaining to the equity component of its capital structure, and the inclusion of commercial paper in the cost of long term debt calculations. The ALJ found that no adjustment should be made to the equity rate of return to reflect the inclusion of the income tax allowance and SFPP was entitled to the income tax allowance. In general the ALJ found that SFPP's application of the Massachusetts Formula was appropriate and complied with Commission precedent. Further, the ALJ agreed with SFPP that environmental remediation costs should be part of the cost of service because there were real and recurring costs that would continue for at least 10-15 years. Finally, the ALJ determined that the just and reasonable rates were those calculated after the adjustments were made consistent with his findings. (SFPP, LP, 129 FERC ¶63,020) (ip access users) (Intelliconnect)

Transfer of Responsibility for Gas Line Repair from Consumer OK’d
A decision by the Ohio Public Utilities Commission to make Columbia Gas of Ohio, Inc., responsible for the repair and replacement of hazardous gas service lines that were formerly the responsibility of the consumer was upheld by the Ohio Supreme Court. The service lines run from the curb to the homeowner’s meter, and before the Commission’s decision, a homeowner was responsible for repairing or replacing a damaged service line, and service was terminated until the repair or replacement was complete. During the period 2000 to 2006, at least four risers for service lines failed, resulting in explosions. The court found that the Commission had the statutory authority to make Columbia responsible for the lines’ repair or replacement. In addition, the record showed that the present system had resulted in serious safety problems and that the Commission’s solution would reduce the hazards. (Utility Service Partners, Inc. v. Pub. Utilities Comm’n of Ohio (OhioSCt) CCH Utilities Law Reporter ¶27,080)

Jordan Cove LNG Import Terminal Authorized
The Jordan Cove Energy Project, L.P., a new liquefied natural gas (LNG) import terminal and the related Pacific Connector Gas Pipeline, LP, were approved by the Commission. The projects were meant to serve the growing energy demand in the Pacific Northwest. The Jordan Cove LNG import terminal would be located in the North Spit of Coos Bay in Coos County, Oregon, and would provide up to 1 billion cubic feet of gas per day to customers in the Pacific Northwest through interconnections with several existing pipeline systems. The 234-mile Pacific Connector pipeline would transport the gas from the terminal to a point near Malin, Klamath County, Oregon, on the Oregon/California border. The Commission found that Jordan Cove's LNG import terminal was consistent with the public interest. Further, the Pacific Connector Gas Pipeline was required by the public convenience and necessity under the Natural Gas Act. (Pacific Connector Gas Pipeline, LP, et al., 129 FERC ¶61,234) (ip access users) (Intelliconnect)

Service Companies

Filing of Form No. 60 by Service Companies Required
Every centralized service company that provides non-power services to any public utility, natural gas company, or both, will be required to file Form No. 60 (Annual Report of Centralized Service Companies) annually and abide by the Uniform System of Accounts, unless exempted or granted a waiver pursuant to agency regulations. A centralized service company is defined to include any service company providing services such as administrative, management, financial, accounting, and other services to other companies in the same holding company system. To clarify a potential gap in its regulations, the Commission will apply these requirements to any centralized service company that provides non-power services to any public utility or any natural gas company, or both, in the same holding company system, so that the filing requirements will apply to all the entities that the Commission envisioned covering in its earlier orders. (FERC Statutes and Regulations Edition ¶31,300) (ip access users) (Intelliconnect)

Hydroelectric Projects

FERC License Surrender Order Upheld
An order by the Federal Energy Regulatory Commission (FERC) granting a licensee’s application to surrender its license was valid because the North Carolina water quality certification upon which it was based was not invalid, the U.S. Court of Appeals for the District of Columbia Circuit ruled. Jackson County had challenged FERC’s decision to allow Duke Energy Carolinas, LLC, to surrender its license to operate the Dillsboro hydroelectric project and to remove the project’s dam and powerhouse. However, the court found that the state’s failure to comply with the statutory notice requirement was harmless because the county had timely actual notice of the state certification application when it was served with a stamped copy. Furthermore, FERC’s environmental assessment was not improperly carried out and did not overlook valid alternatives. Finally, FERC lacked authority to order the licensee to continue to maintain and monitor the facilities. (County of Jackson v. FERC (DCCir) CCH Utilities Law Reporter ¶14,758)

Nuclear Power

Utility Entitled to $38M for DOE’s Failure To Accept SNF
A utility was entitled to damages totaling nearly $38 million because of the Department of Energy's (DOE) failure to accept the utility’s spent nuclear fuel (SNF) and high-level radioactive waste on a timely basis. The federal government, which had a long-established responsibility for the permanent disposal of these wastes, partially breached a 1983 contract that it signed with the utility in which the government agreed to dispose of the company’s SNF beginning no later than January 31, 1998. As a result, the utility was entitled to reimbursement for the mitigation costs it incurred, largely through the reracking of spent fuel casks in its spent fuel pool and private fuel storage. These decisions were reasonable: they prevented the shutdown of the power plant and their costs were demonstrated with reasonable certainty. In addition, they were reasonably foreseeable by DOE at the time of contracting as a logical consequence if the agency breached its contracts with the utility. (Dairyland Power Co-op v. U.S. (ClCt), CCH Nuclear Regulation Reporter ¶20,693)

Further Requirements To Retard Reactor Vessel Aging Adopted
Alternate requirements that pressurized-water reactor (PWR) licensees could use to account for some effects of aging on their reactor vessels have been adopted by the Nuclear Regulatory Commission. The new rule will increase the level of realism used in calculations that examine a PWR's susceptibility to a phenomenon known as pressurized thermal shock (PTS). This action is desirable because the existing requirements are based on unnecessarily conservative probabilistic fracture mechanics analyses. The rule will allow licensees of operating PWRs to adopt voluntarily a more realistic technical approach for determining the probability of vessel failure during a PTS event. This revised approach was derived using data from research on currently operating PWRs that indicate the overall risk of PTS-induced vessel failure after 60 years of reactor operation is much lower than previously estimated. If a licensee chooses to adopt the new approach, the rule would require PWR operators to perform detailed analysis of both reactor vessel surveillance data and the results of regular reactor vessel inspections. If the analysis reveals that certain stress limits have been exceeded, the operator must take steps to either limit the reactor vessel's exposure to neutron radiation (which can make the vessel brittle) or determine how the reactor's systems can be modified to prevent PTS-induced vessel failure. (CCH Nuclear Regulation Reports, No. 1432, January 12, 2010)