|
From the editors of Wolters Kluwer Law & Business, this update describes
important developments from CCH energy publications.
If you have any comments or suggestions concerning
the information provided or the format used, we'd like to hear from you.
Please send your comments to pamela.maloney@wolterskluwer
Nuclear Power
NRC Properly Licensed
Private Firm to Enrich Uranium
A license for a privately owned
new facility in New Mexico to produce enriched uranium as fuel for nuclear
reactors was properly issued by NRC, the U.S. Court of Appeals for the District
of Columbia Circuit ruled. Two public interest groups objected to the license,
claiming that NRC violated the National Environmental Policy Act because
it failed to adequately address the environmental consequences of disposing
of the facility’s uranium waste and violated the Atomic Energy Act
because it accepted the owner’s waste disposal strategy and disposal
cost estimate, which the groups believed were incomplete and unreasonable,
respectively. However, contrary to the group’s environmental argument,
NRC thoroughly examined the environmental consequences of waste disposal
from the facility. With regard to the owner’s waste disposal strategy,
a license applicant must only present a plausible (not a concrete) plan
for the disposition of the depleted uranium wastes. An applicant must also
present a reasonable estimate of disposal costs and give adequate assurances
that it can pay those costs. NRC concluded that the applicant met both of
these criteria—the plausible strategy being disposal by DOE (which
was legally required to take title at the owner’s request) and providing
a cost estimate that included a 25 percent contingency factor above DOE’s
estimate of disposal costs. (Nuclear Information and Resource Service and
Public Citizen v. NRC and U.S., CCH Nuclear Regulation
Reporter ¶20,681)
NRC to Continue Expanded Oversight
of Indian Point in 2008
The Nuclear Regulatory Commission
will continue to conduct additional inspections at the Indian Point nuclear
power plant throughout 2008 to ensure that issues associated with on-site
groundwater contamination and the facility’s new siren system are
being properly addressed. Entergy Nuclear operates Indian Point, which
is located in Westchester County, New York. Although, overall, NRC considers
Entergy’s operation of Indian Point to be acceptable, the agency
also believes that these two issues present unique challenges to the NRC’s
regulatory oversight of the plant. In the near future, Entergy is expected
to submit to the NRC a final report regarding its efforts to characterize
on-site ground water contamination. With regard to the siren system, NRC
continues to work with the Federal Emergency Management Agency, the state
of New York, and local counties to monitor Entergy’s progress in
resolving technical issues that must be addressed before the system can
be placed in operation. (CCH Nuclear Regulation Reporter, No.
1384, January 15, 2008)
Electric Utilities
FERC Adequately Explained Denial of
TEP Remedial Measures
The Federal Energy Regulatory
Commission's (FERC) denial of a remedy for transmission facility owners
(load-serving entities (LSEs)) who complained the New York Independent
System Operator (NYISO) violated its tariff and “operated under
several market design flaws” by failing to accept bids from other
qualified suppliers was not arbitrary and capricious or contrary to law,
the U.S. Court of Appeals for the District of Columbia Circuit held. The
court found that FERC had remedial discretion in determining whether to
require refunds, and that FERC’s explanation for the exclusion of
a certain reserve source from the reserve market was a rational explanation
and was due deference. The court also rejected the LSEs’ challenge
to FERC's decision on remand not to order refunds for high spinning reserve
(SR) prices. The court determined that FERC considered the relevant factors,
balancing the several interests at stake, before concluding that the refunds
were not appropriate. FERC's decision was consistent with the FPA's ``core
purpose'' as the FPA has multiple purposes in addition to preventing excessive
rates, including protecting against inadequate service. FERC's explanation
of the need to protect the availability of high quality SR provided a
reasoned basis for not ordering refunds, according to the court. (Consolidated
Edison Co. of New York, et al. v. FERC (DCCir), CCH Utilities
Law Reporter ¶14,680)
Market-Based Rate Policy for Electricity
Wholesalers Clarified
In response to uncertainties
regarding Order No. 697, Market-Based Rates for Wholesale Sales of Electric
Energy, Capacity and Ancillary Services by Public Utilities (CCH
FERC Statutes and Regulations Edition ¶31,252), the Commission
has issued the following clarifications:
- Sellers are required to comply with all
of the requirements of Order No. 697 as of September 18, 2007, the effective
date of the rule, even if they have previously-approved tariff provisions
to the contrary;
- Both transmission-owning utilities with
market-based rate authority and their affiliates with market-based rate
authority are required to file updated market power analyses for the
Commission’s regional review;
- The Commission will require the use of actual
historical data through November of the previous calendar year, including
data from December of the prior year, for both the horizontal market
power screens and the Delivered Price Test analysis; and
- "Seller-specific terms and conditions"
are those tariff provisions that are commonly found in power sales agreements,
such as creditworthiness, force majeure, dispute resolution, billing
and payment provisions (Market Based Rates for Wholesale Sales of Electric
Energy, Capacity, and Ancillary Services by Public Utilitie,s December
20, 2007.
Natural Gas
FERC’s Deference to Gas Company’s
Standards Affirmed
The Federal Energy Regulatory
Commission's (FERC) allocation of the burden of proof in a proceeding
addressing issues related to establishing natural gas quality and interchangeability
tariff standards to accommodate the introduction of re-gasified natural
gas (LNG) into the market area of Florida Gas Transmission Co., LLC (Florida
Gas), was appropriate and consistent with FERC policy. In FERC Opinion
495 [see CCH Utilities Law Reporter ¶14,641], FERC affirmed an administrative
law judge's (ALJ) decision to accept as just and reasonable Florida Gas's
proposed interchangeability standards, but found that these standards
should be applied to all gas entering the market area, not just to LNG.
On rehearing, generator companies (Generators), consisting of Florida
Power & Light Co., Florida Gas Utility, and Seminole Electric Cooperative,
Inc., argued that FERC erred in deferring to Florida Gas's proposed standards
rather than crafting its own remedy based on the best approach presented.
FERC, however, correctly stated its policy as set in its own precedent,
which held that to the extent a pipeline's NGA section 5 proposal was
just and reasonable, FERC would approve it even if other just and reasonable
remedies existed. Also, the policy did not blur the distinctions between
NGA sections 4 and 5, according to FERC, but was consistent with the structure
of the NGA in delegating to the pipeline the primary initiative to propose
rates, terms, and conditions for services on its own system. Moreover,
the Generators did not provide any reason for FERC to deviate from its
policy. FERC also addressed in its order on rehearing in Opinion No. 495-A,
issues pertaining to the appropriate Wobbe Index range; the appropriate
Wobbe Index rate of change; constituent limits relating to propane, ethane,
and sulfur; the application of the gas quality and interchangeability
standards to gas entering the market area from the western division, and
mitigation costs. Florida Gas also sought rehearing on its alleged right
to receive low Btu gas. (AES Ocean Express LLC v. Florida Gas Transmission
Co., et al., FERC Opinion No. 495-A, 121 FERC ¶61,267 and CCH
Utilities Law Reporter ¶14,681)
FERC Launches Plans for Increased Transparency
in Gas Markets
The Federal Energy Regulatory
Commission (FERC) has approved a final rule and proposed a new rule to
increase transparency in the wholesale markets for physical natural gas.
While the final rule will require certain natural gas market participants
to file information annually on their wholesale, physical natural gas
transactions, the proposal seeks public comment on a plan to require both
interstate and certain major, non-interstate pipelines to post daily information
on capacity, actual flows and scheduled flows. The new rule, Docket No.
RM07-10-000, will require certain natural gas market participants to file
information annually on their wholesale, physical natural gas transactions.
The new form, Form No. 552, must be filed by May 1 of each year, starting
in 2009 for transactions delivered in the previous year. For its proposal,
FERC is seeking comment on requiring both interstate and certain major
non-interstate pipelines to post on a daily basis capacity, scheduled
flow information, and actual flow information. FERC suggests that the
proposal would facilitate transparency of price and availability of natural
gas by providing a complete picture of daily supply and demand information
across the United States. Comments on the proposed pipeline posting requirements
are due February 21, 2008, and must cite the docket number, RM08-2-000.
(CCH FERC Statutes and Regulations Edition ¶31,260
(ip
access user) and ¶32,626
(ip
access user); CCH Utilities Law Reporter ¶5803)
Belle Fourche’s TSA for Expansion
Capacity Invalid
Certain provisions of Belle
Fourche Pipeline Company’s transportation service agreement (TSA)
for expansion capacity offered during its 2007 open season to determine
shipper interest in expanded capacity have been ruled invalid by the Commission.
Nexen Marketing U.S.A. Inc. brought a complaint before the Commission
alleging that Belle Fourche’s TSA violated the Interstate Commerce
Act (ICA), was discriminatory and unlawfully abrogated shippers’
rights. Nexen’s major allegation was that by applying its current
prorationing procedures to the allocation of expansion capacity during
the open season, Belle Fourche provided an undue preference for its historic
shippers and limited new shippers (of which Nexen was one) to no more
than 10 percent of expansion capacity. (Nexen Marketing U.S.A., Inc.
v. Belle Fourche Pipeline Co. 121 FERC ¶61,235.
Oil & Gas
MMS Addresses Issues Related to Oil
Royalties
The Minerals Management Service
has issued a final rulemaking regarding its regulations dealing with valuation
of oil produced from Indian leases for royalty purposes to replace the
1988 Indian Oil Rule. Indian lease oil will now be valued at the gross
proceeds received by the lessee or its affiliate in an arm's-length sale,
rather than using NYMEX or spot prices. MMS states that virtually all
Indian lease oil is sold in arm's length transactions at the lease, whereas
much of other federal oil leases are transported before an arm's-length
sale.
MMS has also proposed amendments to the rules
governing royalty relief for deepwater oil and gas leases on the Outer
Continental Shelf (OCS). A federal court of appeals found that MMS regulations
implementing the Deep Water Royalty Relief Act were inconsistent with
the statute, forcing MMS to rewrite the regulations. The proposed rules
would conform the regulations to follow the court's decision, meaning
that more leases would be eligible for royalty relief, costing the government
an estimated $3.1 billion to $10.3 billion between 2000 and 2034.
Lessees, operators, pipeline right-of-way holders,
and permittees would be required to submit payments for cost recovery
service fees electronically, under another MMS proposal. This would apply
to fees for the processing of plans, applications, and permits. The federal
government maintains a secure web site to accept credit card and Automated
Clearing House (ACH) payments, and 94 percent of MMS cost recovery fees
currently being paid are paid electronically. If the proposal were to
become finalized, checks, money orders, and cashier's checks would not
be accepted after the rule's effective date.
Finally, MMS is also is requesting comments
from interested parties regarding the experiences of refiners who qualify
under the Royalty-in-Kind (RIK) program in gaining access to adequate
supplies of crude oil in the marketplace at equitable prices. Under the
RIK program, the Department of the Interior can take federal royalty crude
oil in kind, instead of royalty payments, and sell it to eligible refiners,
which are those that are considered small and independent. MMS notes that,
as of October 2007, only two refiners were participating in the program.
MMS is preparing a new Determination of Need to decide whether the federal
government should continue selling federal royalty crude oil under the
RIK eligible refiner program. (CCH Energy Management
¶9530, 9316, 9315, and 9791, respectively).
|