|
From the editors of Wolters Kluwer Law & Business, this update describes
important developments from CCH energy publications.
If you have any comments or suggestions concerning
the information provided or the format used, we'd like to hear from you.
Please send your comments to pamela.maloney@wolterskluwer
Nuclear Power
More Assurances for Decommissioning
Plans Proposed
Environmental and financial
improvements to the decommissioning planning process have been proposed
by the Nuclear Regulatory Commission (NRC) to reduce the likelihood that
any current operating facility will become a legacy site—a facility
whose owner, faced with complex radiological issues, cannot complete the
decommissioning process for technical or financial reasons. Facilities
that process large quantities of material, especially in liquid form,
have the potential for significant environmental contamination through
leakage. The proposed rule would require licensees to conduct their operations
in a manner that would minimize the introduction of residual radioactivity
into all strata of the site, including the subsurface soil and groundwater.
Licensees would also be required to survey certain concentrations of residual
activity, including those in subsurface areas, and keep records of these
surveys along with other records important for decommissioning. (CCH
Nuclear Regulation Reporter ¶4233)
$1.02 Billion NRC Budget Proposed for
2009
The Bush administration has
proposed an NRC budget of $1.02 billion for fiscal year 2009. Approximately
$91 million more than the 2008 agency allocation, the budget would continue
to be funded in large part through user fees, which are estimated at $856
million for the year. The additional funds reflect increased regulatory
activities, driven primarily by continued industry interest in constructing
new nuclear facilities, oversight of existing reactors, and materials
and waste licensing. Among budget highlights, the agency allocation for
nuclear reactor safety would be increased by $76 million over the 2008
appropriation, to over $787 million, including approximately $237.5 million
for new reactor activities. $221.3 million has also been requested by
the Commission for the nuclear materials and waste safety program, which
is an increase of $21 million over the previous year. The allocation would
be used to conduct regulatory programs at fuel cycle facilities, provide
for pre-licensing activities at the proposed Yucca Mountain repository,
and support programs for nuclear materials users. (CCH Nuclear
Regulation Reports, No. 1386, February 12, 2008)
Electric Utilities
Three NERC Electric Reliability Standards
Approved
Three new planning and operating
reliability standards have been approved by the Commission to further
ensure the reliability of the nation’s bulk power electricity market.
The standards were proposed by the North American Electric Reliability
Corp. (NERC), the FERC-certified electric reliability organization (ERO).
In July 2006, FERC designated NERC as the ERO under Section 215 of the
Federal Power Act, a new provision added by the Energy Policy Act of 2005
to establish a system of mandatory, enforceable reliability standards
under the Commission's oversight (Facilities Design, Connections and
Maintenance Reliability Standards, Order No. 705, 73 FR 1770, January
9, 2008, 121
FERC ¶61,296 (ip
access user)).
New Reliability Standards for Cyber
Security Approved
Eight new mandatory critical
infrastructure protection (CIP) reliability standards to protect the nation’s
bulk power system against potential disruptions from cyber security breaches
have been approved by the Commission. These reliability standards were
developed by the North American Electric Reliability Corporation (NERC),
which the Commission has designated as the electric reliability organization
(ERO) and are the first enforceable reliability standards that address
cyber security concerns in the context of the bulk power system. The mandatory
reliability standards, which take effect April 7, require certain users,
owners and operators of the bulk power system to establish policies, plans,
and procedures to safeguard physical and electronic access to control
systems, to train personnel on security matters, to report security incidents,
and to be prepared to recover from a cyber attack. (Mandatory Reliability
Standards for Critical Infrastructure Protection, 73 FR 7368, February
7, 2008, 122
FERC ¶61,040 (ip
access user)).
FERC Rejects Challenge to PJM Rate
Design.
In finding that PJM Interconnection,
L.L.C.'s (PJM) existing license plate rate design governing the allocation
of costs for existing facilities was not shown to be unjust and unreasonable,
the Federal Energy Regulatory Commission (FERC) affirmed its conclusions
from a prior FERC Opinion [Opinion No. 494 at CCH Utilities Law Reporter
¶14,640]. FERC balanced a variety of conclusions to affirm its earlier
Opinion concerning the regional transmission organization's (RTO) transmission
rate design, including that the existing transmission system was built
to serve local needs, that the transmission system, although integrated,
was not equally available or valuable to all users of the system, the
extensive impact of changing rate design on customers, and the potential
effects of such a change on RTO membership. (PJM Interconnection,
L.L.C., FERC Opinion No. 494-A, CCH Utilities Law Reporter
¶14,684)
Hydroelectric Power
FERC's Denial of Permits, Licenses
for Hydroprojects Okayed
The Federal Energy Regulatory
Commission (FERC) did not err when it denied preliminary permits and licenses
for certain hydroelectric power project applicants to construct and operate
hydroelectric power plants on existing dams, the U.S. Court of Appeals
for the District of Columbia Circuit ruled. FERC denied the permits and
then the licenses because it found the projects' responsible individuals,
who had previous records of noncompliance, unfit. The court said that
FERC could consider fitness in evaluating applications for new permits
and licenses under the Federal Power Act (FPA). Also, the court pointed
out that in considering a license application, FERC assesses the public
interest, broadly defined, and that in deciding whether to grant a permit,
FERC also has discretion to consider the fitness of the applicant. Moreover,
FERC had precedent for looking to the individuals behind the corporation
when deciding on a new license and could base its decision on who would
actually run the project, according to the court. (Energie Group,
LLC, et al. v. FERC (DCCir), CCH Utilities Law Reporter
¶14,682)
Natural Gas
Natural Gas Project Cost Limits Increased
for Inflation
The project cost limits for
construction, acquisition and operation of natural gas facilities authorized
under blanket certificate procedures have been adjusted for inflation
by the Director of the Office of Energy Projects. The automatic project
cost limit was increased from $9.9 million in 2007 to $10.2 million in
2008, while the prior notice project cost limit was increased from $28.2
million to $29 million. The calendar year dollar limit on underground
storage testing and development has been increased from $5.4 million in
2007 to $5,550,000 in 2008. The new limits became effective January 1,
2008. (CCH FERC Statutes and Regulations Edition ¶31,263)
Expanded Scope for Blanket Certificate
Abandonments Affirmed
In an order denying rehearing
of Order No. 686-B [CCH Statutes and Regulations Edition
¶31,255], the Federal Energy Regulatory Commission has affirmed its
controlled expansion of the number of facilities that may be abandoned
pursuant to blanket certificate authority. The Interstate Natural Gas
Association of America (INGAA) and Northern Natural Gas Company (Northern
Natural) argued in their rehearing request that the Commission did not
provide sufficient justification for directing companies to determine
if a facility could be abandoned by comparing the current blanket project
cost cap to an estimate of the cost to replicate an existing facility
today, rather than to the original cost to construct that facility.
INGAA’s and Northern Natural’s
proposal to rely on a facility’s original cost would effectively
lift the lid on the size of projects subject to blanket abandonment authorization,
since the original cost remains fixed while the project cost cap ratchets
up. Thus, over time, companies could abandon increasingly more significant
portions of their systems, particularly their older facilities, such as
mainline installed in the 1930s. If the Commission permitted the scale
of blanket abandonment projects to grow with each annual adjustment to
the blanket project cost limit, it could no longer guarantee that blanket
abandonments would continue to be consistent with the public convenience
and necessity criteria of the Natural Gas Act. (Revisions to the Blanket
Certificate Regulations and Clarification Regarding Rates, 122
FERC ¶61,028 (ip
access user) )
FERC Failed To Distinguish Between
Pipeline Refund Settlement
The Federal Energy Regulatory
Commission (FERC), in reaffirming orders requiring a natural gas producer,
Burlington Resources Inc. (Burlington), to refund excess revenues to two
pipeline gas purchasers and denying effect to settlement between the parties,
failed to explain adequately its approval of similar settlements between
the two pipelines and other gas producers, the U.S. Court of Appeals for
the District of Columbia Circuit held. The court said the distinctions
that FERC provided between the producer's settlement and the other similar
settlements were “illusory,” and, therefore, the court vacated
FERC's orders and remanded the case to the agency. According to the court,
FERC misinterpreted the court's precedent, and this led to FERC's incorrect
reasoning that a settlement of past ad valorem tax disputes was invalid
unless a determination could be made of the precise consideration the
producer gave to satisfy its refund obligations. While it was true that
for each past overpayment the maximum-price rule provided that the purchaser
had a right to a full refund, the court said, the law did not prevent
purchasers from later exchanging those accrued rights for other valuable
consideration. As such, FERC could not insist that the exchange match
the parties' exact obligations. Moreover, the settlement agreements created
no liabilities for future gas sales, but merely resolved disputes over
liabilities already accrued, settling claims of past price-ceiling violations.
(Burlington Resources Inc. v. FERC (DCCir), CCH Utilities
Law Reporter ¶14,683)
Oil and Gas
BLM Amends Alaska National Petroleum
Reserve Rules
Changes to oil and gas administrative
procedures for the National Petroleum Reserve-Alaska implementing amendments
to the Naval Petroleum Reserves Production Act of 1976 that were changed
by the Energy Policy Act of 2005 (EPAct 2005) have been issued by the
Bureau of Land Management. BLM may waive, suspend, or reduce the rental,
royalty, or minimum royalty on leases in the NPR-Alaska if necessary to
promote development or if BLM determined the lease could not be successfully
operated under the lease terms. The provision is intended to keep open
producible wells that would otherwise be shut in. BLM may require additional
bonding for any NPR-Alaska lease if BLM determined that the operator posed
a risk, including factors such as a history of previous violations, an
MMS notice of uncollected royalties due, or if BLM estimates the cost
of plugging existing wells and reclaiming lands exceeded the present bond
amount. BLM is required to extend lease terms as long as oil and gas is
produced from the lease in paying quantities or drilling or re-working
operations, actual or constructive, are being conducted on the lease.
The final rule has added the requirement that BLM grant an extension when
it has determined that oil or gas is capable of being produced in paying
quantities from the lease. NPR-Alaska leases expire on the 30th anniversary
of their original issue date unless oil or gas is being produced from
the lease, up from ten years before the passage of EPAct 2005. (Energy
Management ¶9531)
Credits for Relinquishing Leases Offshore
Florida Proposed
Certain leases located offshore
of Florida would be eligible for a bonus or royalty credit if relinquished,
under a proposal from the Minerals Management Service. The proposed rule
is designed to implement the Gulf of Mexico Energy Security Act of 2006.
The law defined leases eligible for the credits as those in existence
on the date of the law's enactment that were located within certain OCS
planning areas as well as within specified distances from the Florida
coastline. The credit would be equal to the original bonus paid plus the
cumulative rental paid on the lease since its issuance, not including
any exploration costs or interest costs. To obtain the credit, parties
holding title would be required to apply within one year from the effective
date of the final rule. Multiple owners of a lease would receive a percentage
share of the credit based upon their percentage share in total ownership
interest at the time the request is submitted to MMS. A bonus or royalty
credit could be applied to a successful bid for a new lease or for royalties
reported due on Form MMS 2014. The credits could be redeemed only in lieu
of a monetary payment owed, and not for any royalty-in-kind deliveries.
The credits would have no expiration date, but MMS proposes that it be
permitted to apply any unused credits after five years to the credit holder's
obligations to MMS at the discretion of MMS. Credits would be transferable.
(Energy Management ¶9317)
|