December 2008


From the editors of Wolters Kluwer Law & Business, this update describes important developments from CCH energy publications.

If you have any comments or suggestions concerning the information provided or the format used, we'd like to hear from you. Please send your comments to pamela.maloney@wolterskluwer


Nuclear Power

DOE Cites Need for Second SNF Repository
The President and Congress have been informed of the need for a second geologic repository for spent nuclear fuel (SNF) and high-level radioactive waste (HLW) by the Secretary of Energy. ``Unless Congress raises or eliminates the current statutory capacity limit of 70,000 metric tons of heavy metal [MTHM], a second repository will be needed,’’ Secretary Bodman said. ``The statutory limit is not based on any technical considerations, and the repository layout at Yucca Mountain can be expanded to accommodate three times the amount of fuel allowed under the current arbitrary cap.’’ Currently, the inventories of commercial and federal government SNF and HLW in the United States are projected to exceed 70,000 MTHM by 2010. Assuming all existing operating commercial nuclear reactors in the United States request license extensions from the Nuclear Regulatory Commission to operate for 60 years, the projected amount from these reactors requiring disposal is estimated to be approximately 130,000 MTHM. (CCH Nuclear Regulation Reports, No. 1407 December 23, 2008)

Security Requirements for Nuclear Power Plants Expanded
Security requirements for nuclear power reactors have been enhanced by the Nuclear Regulatory Commission. Significant features in the new rule include a safety/security interface section that requires plants to manage plant activities to avoid potential adverse interactions between security activities and other plant activities. Additionally, there are new sections requiring a comprehensive cyber security program at nuclear power plants, and a requirement that plants develop strategies and response procedures to address an aircraft threat or loss of large areas of the facility due to explosions and fire. New training and qualification requirements for security personnel are also included. The new rule will go into effect 30 days after its publication in the Federal Register. (CCH Nuclear Regulation Reports, No. 1407 December 23, 2008)

Electric Utilities

Revenue Sufficiency Guarantee Unjust and Unreasonable
In the paper hearing ordered by the Commission (125 FERC ¶ 61,126 (ip access users)), the Commission found that the real-time Revenue Sufficiency Guarantee charge contained in the Midwest Independent Transmission System Operator, Inc.’s (Midwest ISO) Transmission and Energy Markets Tariff (tariff) was unjust and unreasonable, that proposed alternative cost allocations were just and reasonable, and required refunds. The Revenue Sufficiency Guarantee charge allows generators to recover start-up, no-load and incremental costs that generators did not recover in the locational marginal price in the real-time market. The Commission found that the tariff, which only allocated Revenue Sufficiency Guarantee costs to market participants that withdrew energy, was not based on cost causation because virtual supply offers could cause unit commitment and Revenue Sufficiency Guarantee costs, whether the virtual supply offers were made by financial trader market participants (who did not withdraw energy) or other participants with physical load and generation (who did withdraw energy). The Commission required a new tariff deleting the “actually withdraws energy” language and inserting “cleared” before virtual offers. Also, the Commission found that refunds were appropriate because the current tariff had been unduly discriminatory. The Midwest ISO was required to resettle Revenue Sufficiency Guarantee costs among market participants reflecting the revised cost allocation approved by the Commission. (Ameren Services Co., et al. v. Midwest Independent Transmission System Operator, Inc., 125 FERC ¶61,161 (ip access users))

Natural Gas

Market-Based Pricing for Short Term Capacity Releases Affirmed
The market-based pricing provisions for short term capacity releases and other changes affecting short term transportation services on interstate natural gas pipelines established in Order No. 712 (CCH FERC Statutes and Regulations Edition ¶31,271 (ip access users)) have been affirmed by the Commission. In its review of Order No. 712 (Order No. 712-A, effective December 31, 2008), the Commission denied rehearing on a number of specific issues, but did grant clarification of certain questions, particularly in the area of asset management arrangements (AMAs). With regard to price ceilings applicable to pipeline capacity, the Commission denied rehearing requests and continues to find that the maintenance of the maximum rate ceilings for pipeline short term transactions is necessary to protect against the potential exercise of market power. Similarly, rehearing was denied with regard to the exercise of market power by withholding capacity because the Commission has a sound basis for not removing from pipeline services the recourse rate, which acts as a check against both the market power of the releasing shippers and the pipelines themselves in situations in which insufficient competition exists. Order No. 712’s posting requirements were also affirmed—the specific days or months during which an AMA manager’s delivery/purchase obligation is in effect need to be posted. (CCH FERC Statutes and Regulations Edition, No. 502, December 22, 2008)

Incremental Rates Discriminate Against Successor Customers
Transcontinental Gas Pipe Line Corporation (Transco) could not charge new customers higher rates for base gas than former customers, according to the Commission. Although the Commission found that Transco’s tariff requiring new customers to pay incremental rates based on the full cost of the replenishment base gas was not unjust or unreasonable, it nonetheless ordered that the costs of base gas purchases be rolled-in equally to the rates of all Transco customers. Transco proposed a new rate system that would pass along the increased cost of gas to its customers who purchased base gas. Transco proposed to charge successor customers higher incremental tariff rates than it had charged former customers because of the increased cost of injecting new base gas to replenish the tanks. The Commission held that Transco did not prove that its incremental tariff rates were just and reasonable because the rates did not reflect actual costs caused by successor customers. Although the successor customers did not prove that Transco’s base gas purchase option provisions were unjust and unreasonable, the Commission found the provisions outdated and ordered the parties to re-negotiate in light of the changed financial times. (Transcontinental Gas Pipe Line Corp., 125 FERC ¶ 63,020 (ip access users))

Hydroelectric Power

Reconstruction of Hydro Project Not Subject to NEPA Regulations
A Federal Energy Regulatory Commission (FERC) order granting a company the right to rebuild a hydroelectric generating plant did not violate the National Environmental Policy Act (NEPA), the U.S. Court of Appeals for the Eighth Circuit has determined. Two citizens groups who argued that relicensing the Project was a “reasonably foreseeable future action” challenged FERC’s decision stating that NEPA required FERC to consider the cumulative impact to the environment from reconstruction and operation. FERC concluded that reconstruction would not influence its relicensing determination and held that the compliance regulations governing reconstruction under the existing license were separate and distinct from the more stringent regulation governing relicensing; thus, FERC’s decision not to include the impacts of relicense operation in its environmental assessment of reconstruction was not arbitrary or capricious. (Missouri Coalition for the Environment, et al. v. FERC, et al., (8th Cir. 2008) CCH Utilities Law Reporter ¶14,719).

Oil Pipelines

MMS Failed To Take ``Hard Look'' at Proposed Exploration Plan
Environmental and citizen group's Outer Continental Shelf Lands Act (OCSLA) claims against the Mineral Management Service (MMS) alleging that it failed to take a ``hard look'' at an oil company's proposed test well drilling plan were not barred by the OCSLA's time limitation, the U.S. Court of Appeals for the Ninth Circuit held. The OCSLA required that a petition for review be filed with the court within 60 days of any contested action. The groups first filed an administrative appeal with the Interior Board of Land Appeals (IBLA). However, the court found that the groups did not relinquish their opportunity for judicial review by opting to file an administrative appeal first. The court went on to find that, MMS failed to properly determine if the effects of the oil company's project were ``significant,'' as determined under the National Environmental Policy Act. To determine if a project's effect was significant, the MMS had to consider both the context and intensity of the proposed action. MMS's environmental assessment (EA) failed to take a hard look at whether the company's exploratory drilling program would have a ``significant'' effect on bowhead whales, an endangered species. The court also found that MMS acted in contravention of the regulations by approving the three-year plan without determining the locations of the wells that the company would drill during that period. MMS must prepare a revised EA or, as necessary, an EIS the court concluded. (CCH Energy Management, Alaska Wilderness League, et al. v. Dirk Kempthorne, at al., 9th Cir., CCH Energy Management ¶9604).