August 2008


From the editors of Wolters Kluwer Law & Business, this update describes important developments from CCH energy publications.

If you have any comments or suggestions concerning the information provided or the format used, we'd like to hear from you. Please send your comments to pamela.maloney@wolterskluwer


Nuclear Power

DOE: Yucca Mountain Project to Cost $96 Billion
The total system life cycle cost for the geologic repository at Yucca Mountain, Nevada, will be $96.2 billion, according to a newly revised estimate released by the Department of Energy (DOE). The 2007 total life cycle estimate includes cost to research, construct and operate Yucca Mountain over a period of 150 years, from the beginning of the program in 1983 through closure and decommissioning in 2133. The $96.2 billion figure represents a 38 percent increase from the last published estimate (in 2001) of $57.5 billion. The updated estimate takes into account a substantial increase in the amount of waste to be shipped and stored at the repository—from a 2000 estimate of 83,800 metric tons heavy metal to a 2007 estimate of 109,300 metric tons heavy metal—and more than $16 billion for inflation. The Department is not proposing a change in the fees paid by nuclear utilities for the disposal of commercial spent nuclear fuel. (CCH Nuclear Regulation Reporter, No. 1398, August 12, 2008)

Nuclear Plant’s Rates Remain Unchanged
The Louisiana Public Service Commission’s (Louisiana Commission) request to alter the depreciation and decommissioning rates and the return on equity (ROE) under the Unit Power Sales Agreement (Agreement) between System Energy Resources, Inc. (System Energy) and four Entergy operating companies to reflect a possible change in the length of an operating license was denied by the Federal Energy Regulatory Commission (Commission). Louisiana Commission filed the complaint against System Energy requesting the rate change in anticipation of a 20-year extension in the operating license of the Grand Gulf 1 Nuclear Generating Facility. Also, Louisiana Commission argued the ROE formula rate should be lowered because it was no longer just and reasonable based on the decline in interest rates since System Energy’s last proceeding. The Commission denied Louisiana Commission’s complaint on both grounds. The Commission noted that in order for the complainant to succeed Louisiana Commission had to establish that the current rate was unjust and unreasonable; second, the complainant had to establish that its alternative rate proposal was just and reasonable. The Commission found that Louisiana Commission did not meet the first burden because it did not demonstrate that the depreciation and decommissioning rates under the Agreement were not just and reasonable, or that System Energy’s ROE should have been reduced from its level. Louisiana Commission did not meet the second burden by not providing sufficient evidence to demonstrate that its proposed rates for the Agreement were just and reasonable. Finally, the Commission found that Louisiana Commission had not provided sufficient information to establish that System Energy’s currently-effective ROE under the Agreement was unjust and unreasonable, or that its proposed ROE would be just and reasonable.( Louisiana Public Service Commission v. System Energy Resources, Inc., et al., 124 FERC ¶61,003 (ip access users))

Natural Gas

Non-jurisdictional Extension Line Costs Removed from Recourse Rates
The construction costs of non-jurisdictional natural gas extension lines which would connect a lateral expansion project (Colorado Lateral) to a local distribution company will be removed by the Commission from the cost-based recourse rates that the transmission company constructing the lines will charge for service. In an order on rehearing of Kinder Morgan Interstate Gas Transmission LLC (122 FERC ¶61,154 (ip access users)), the Public Service Company of Colorado (PSCo) argued that the Commission erred in permitting Kinder Morgan to include the costs of these lines in both the initial incremental negotiated and recourse rates that it will charge for this service. The distribution company currently obtains its gas transportation service from PSCo; when the Colorado Lateral and the non-jurisdictional extension lines are completed, it will be able to serve its market via Kinder Morgan’s Colorado Lateral, thus effectively bypassing PSCo. Kinder Morgan intends to convey ownership of the extension line facilities to the distribution company before service begins. In this instance, Kinder Morgan is building the Colorado Lateral to service a single shipper and the Commission has approved an initial incremental recourse rate for service to that shipper. Therefore, the construction costs associated with the non-jurisdictional facilities would be included in Kinder Morgan’s incremental recourse rate as soon as service began on the Colorado Lateral. Since the distribution company has not subscribed to the full capacity of the Colorado Lateral until the second five-year period of operation, it is possible that another shipper seeking to acquire available capacity on this incrementally-priced line would be required to pay for extension line facilities that are not owned and operated by Kinder Morgan and that would not benefit such shipper. Therefore the costs associated with the non-jurisdictional facilities must be removed from the recourse rates. The Commission will not require Kinder Morgan to remove these costs from negotiated rates for service on the Colorado Lateral because these rates were freely negotiated (Kinder Morgan Interstate Gas Transmission LLC, 124 FERC ¶61,024 (ip access users))

Unsafe Gas Leakage Stalls LNG Expansion Project
As part of a Federal Energy Regulatory Commission (FERC) order approving a project expanding the liquefied natural gas (LNG) capacity of an LNG terminal, FERC's conclusion that unblended LNG would not have caused leaks in a local natural gas distribution company's distribution system if a subset of the system's compression couplings had not been damaged by hot tar applied to the couplings during their installation decades earlier was supported by substantial evidence, the U.S. Court of Appeals for the District of Columbia Circuit held. The distribution company, Washington Gas Light Company (WGL), argued that the expansion project would be inconsistent with the public-interest requirements of the Natural Gas Act (NGA) because the influx of unblended LNG would cause severe leakage throughout its distribution system. The court found, however, that the facts were consistent with FERC's finding that WGL's couplings were so damaged by the hot tar that its distribution system became susceptible to the confluence of multiple leak-inducing factors, such as LNG and cold weather. Nonetheless, the court granted WGL's petition for review, vacated FERC's orders to the extent that they approved the expansion project, and remanded the case to FERC because FERC failed to ensure that the project could go forward consistent with the NGA’s public interest requirement by concluding that WGL could address safety concerns before the project's November 2008 in-service date without the support of substantial evidence. (Washington Gas Light Co. v. FERC (DCCir), CCH Utilities Law Reporter ¶14,703)

Electric Utilities

Entergy Violated Tariff by Canceling Transmission Service Agreements
The termination of two firm point-to-point transmission service agreements between ConocoPhillips Company (ConocoPhillips) and Entergy Services, Inc. (Entergy) was a violation of Entergy’s Open Access Transmission Tariff (OATT) the Commission ruled. ConocoPhillips requested and received a total of 103 megawatts (MW) of short-term firm point-to-point transmission service on Entergy’s system. A month later, Entergy’s Independent Coordinator of Transmission (ICT) learned that Entergy had oversold service at the Entergy-Ameren interface because it miscalculated the Available Flowgate Capability (AFC) due to a software error. The ICT resolved the oversell by recalling (i.e., terminating) transmission in reverse queue order, thereby terminating ConocoPhillips firm service. ConocoPhillips then filed a complaint with the Commission. The Commission found that the termination of ConocoPhillips’ transactions was not consistent with Entergy’s OATT. Absent a specific provision addressing software errors, the provision addressing the curtailment of firm transmission service was the appropriate OATT provision to which Entergy and the ICT should have looked for addressing the constraint. Relieving the system constraints through termination of reservations in the reverse order that the requests were accepted did not comply with this provision, and placed the burden of relieving the constraint on ConocoPhillips and the other last-in-queue firm-service customers. This unduly discriminated between customers even though they were similarly situated, each having confirmed service, and as such, action was unsupported by Entergy’s OATT, the Commission reasoned. NRG Power Marketing, LLC (NRG Companies) requested that the Commission’s determination also apply to them. The Commission concluded that it would be inappropriate for them to address NRG Companies request, because NRG Companies were effectively asking to be joined in the complaint and that would be improper. (ConocoPhillips Co. v. Entergy Services, Inc., 124 FERC ¶61,085 (ip access users))

Blanket Authorizations for Mergers/Acquisitions Affirmed
FERC’s recent decision to establish additional blanket authorizations for certain dispositions of jurisdictional facilities under the Federal Power Act’s (FPA) merger and acquisition provisions to facilitate investment in the electric industry [Order No 708, CCH FERC Statutes and Regulations ¶31,265 (ip access users)], has been largely affirmed by the agency. The new rule (Order No. 708-A) affirms the earlier decision’s finding that the transfer of a wholesale power contract which does not provide for the transfer of control of generation or transmission cannot affect horizontal or vertical market power because the parties which sought rehearing on the issue raised no new arguments to the contrary. It also affirms Order No. 708’s decision to grant blanket authorization for hedging transactions—those that employ an approach to risk management that uses financial instruments to manage identified risk. Blanket authorization involving hedging for holding companies is in the public interest because such authorization would not give the acquiring entity additional market power or enable it to undermine competition or place its captive customers at a disadvantage. Finally, FERC clarifies that blanket authorization applies to transactions involving the transfer of assets from one non-traditional utility subsidiary (i.e., a public utility that does not have captive customers and does not own or control transmission facilities) to another non-traditional utility subsidiary when only one of the two non-traditional utility subsidiaries survives the transaction. The Commission found that this type of transaction is consistent with the public interest and does not entail subsidization issues. (CCH FERC Statutes and Regulations ¶31,273 (ip access users))

New Cross-Subsidization Safeguards Clarified
A number of FERC’s cross-subsidization restrictions on affiliate transactions [Order No 707, CCH FERC Statutes and Regulations ¶31,264 (ip access users)], have been clarified on rehearing by the agency. These restrictions encompass transactions between franchised public utilities that have captive customers or that own or provide transmission service over jurisdictional transmission facilities and their market-regulated power sales affiliates or non-utility affiliates. The rule expanded the transactions and entities to which these restrictions apply in order to protect against inappropriate cross-subsidization of market-regulated and unregulated activities by the captive customers of public utilities. In Order No. 707-A, the Commission decided to permit affiliates within a single-state holding company system that does not have a centralized service company to provide at cost to other affiliates in the system the kinds of services typically provided by centralized service companies and the goods to support those services. This permission does not apply to inputs to utility operations such as fuel supply, construction or real estate that have a clearly identifiable market price, nor does it apply to the implementation of major projects that are easily susceptible to competitive bidding, such as construction projects. With regard to multi-state holding companies that do not have centralized service companies, the Commission will consider requests for waiver on a case-by-case basis for at-cost pricing in the multi-state context under the same circumstances as for single-state holding companies (i.e., only for general and administrative services and goods to support those services and only where members of the holding company do not sell such goods outside the holding company.) This will allow the Commission to examine each situation to ensure that adequate regulatory oversight and protections are in place. (FERC Statutes and Regulations ¶31,272)

Alternative Energy

Alternative Energy Program for OCS Proposed by MMS
Regulations that would establish a program to grant leases, easements, and rights-of-way (ROW) for alternative energy project activities on the Outer Continental Shelf (OCS) have been proposed by the Minerals Management Service (MMS). The regulations would also address the alternate use of existing OCS facilities, as well as establish a method for sharing revenues with the coastal states. MMS expects that wind, wave, and ocean currents will be the primary focus of OCS projects in the short term, although it expects solar, hydrogen, and other projects in the future. MMS is proposing two types of alternative energy leases: a commercial lease of up to 25 years for full-scale commercial energy production, and a limited lease of up to 5 years for site assessment, technology testing, and other activities that do not include commercial operations. Leases, ROW grants, and Alternative Use Right of Use and Easement Grants (RUE) are required by the Energy Policy Act of 2005 to be awarded competitively. A cash bonus bidding system would be used as the basis for determining the winner. MMS has proposed a rental fee of $3 to $5 per acre, which is lower than that normally used for oil and gas projects. (CCH Energy Management ¶9320)