April 2007


From the editors of Wolters Kluwer Law & Business, this update describes important developments from CCH energy publications.

If you have any comments or suggestions concerning the information provided or the format used, we'd like to hear from you. Please send your comments to pamela.maloney@wolterskluwer

Nuclear Power

Tighter Design Basis Threat Security Requirements Established
More comprehensive design basis threat (DBT) security requirements have been established by the Nuclear Regulatory Commission. These changes specify the DBT that nuclear power plants and certain related facilities must be able to guard against with a high level of assurance. Plants will be required to defend against one or more assault teams consisting of adversaries who were willing to kill and be killed and who were knowledgeable about specific target selection. They will also have to defend against a wide range of assault weapons and incapacitating agents and protect themselves against assault by land and water vehicles. (Nuclear Regulation Reporter, ¶9302).

NRC: Fuel Leak at Kewaunee Was a Significant Safety Issue
The failure of the operators of the Kewaunee Nuclear Power Plant to promptly evaluate and take action to correct a diesel generator fuel leak in June 2006 was of substantial importance to the safety of the Wisconsin plant, the Nuclear Regulatory Commission has determined. Plant personnel had identified a leak in one of two emergency diesel generators at the plant which supply electrical power to plant safety systems if the normal connection to off-site power sources is lost, but did not follow prescribed procedures to evaluate the condition. They subsequently saw a substantial increase in the fuel leaking from the generator, which was declared inoperable. The utility tested the defective equipment and concluded that the leaking fuel oil systems components would have failed after four hours of diesel operation if the generator was required to supply power to plant safety systems. The utility’s corrective actions included replacing the leaking components and emphasizing to plant personnel the need to follow procedures for entering issues into the plant’s corrective action program. Findings of substantial safety significance normally result in additional NRC inspections and meetings with the utility. (CCH Nuclear Regulation Reports, Number. 1366, April 13, 2007).

Electric Utilities

83 NERC Reliability Rules Approved
In order to assure the reliability of the nation’s bulk power system, the Federal Energy Regulatory Commission has approved 83 reliability standards proposed by the North American Electric Reliability Corporation (NERC), the FERC-certified electric reliability organization. NERC is responsible for developing and enforcing mandatory reliability standards. The standards approved by the Commission include those for resource and demand balancing, critical infrastructure protection, emergency preparedness, and communications. Also, approved were standards for interchange scheduling and coordination, transmission planning and operations, and personnel training and performance. While approving the mandatory reliability standards, FERC observed that much work remained to be done, noting that many of the reliability standards need substantial improvement. (CCH Federal Energy Regulatory Commission Reports—Statutes & Regulations Edition ¶31,242 and 14,250—14,253).

Proposal Would Remove QF Exemption from Reliability Standards
The elimination of the exemptions available to qualifying facilities (QFs) from the recently added electric reliability provisions of the Federal Power Act has been proposed by FERC. According to the Commission, from a reliability perspective, there does not appear to be a meaningful distinction between QF and non-QF generators that would warrant the exemption of QFs from the mandatory reliability standards. Moreover, the Commission believes that the adoption of this proposal would increase the reliability of the North American Bulk Power System. (CCH Federal Energy Regulatory Commission Reports—Statutes & Regulations Edition ¶32,613).

Electricity Task Force Submits Report to Congress
The Electric Energy Market Competition Task Force established under the Energy Policy Act of 2005 to conduct a study of competition in wholesale and retail markets for electricity in the United States has submitted its final report to the U.S. Congress. The report contains the observations of the Task Force on competition in wholesale electric power markets , as well as on retail market competition. The report notes that the goal of increasing competition in electric power markets was to overcome the perceived shortcomings of traditional cost-based regulation. It was expected that in a competitive market environment, prices should guide consumption and investment decisions. Specifically, the report posits that the market-based pricing of electricity will reflect more accurately the underlying costs of production. Ideally, these prices should align the price of electricity with the value customers place on electricity, leading to a more efficient allocation of electrical resources and lower overall prices. (CCH Federal Energy Regulatory Commission Reports—Statutes & Regulations Edition, Number 482, April 19, 2007).

Commission Directs Interconnection/Transmission Services
Brazos Electric Power Cooperative, Inc.’s (Brazos) request for interconnection and transmission services under the Federal Power Act was granted by the Commission when it directed TXU Electric Delivery Company (TXU Electric Delivery) to provide interconnection with Brazos’ proposed transmission line. The Commission also directed TXU Electric Delivery and CenterPoint Energy Houston Electric, LLC (CenterPoint) to provide transmission services for power flows into and out of the Electric Reliability Council of Texas (ERCOT) over Brazos’ proposed transmission line. (Cottonwood Energy Company, LP 118 FERC ¶61,198).

Midwest ISO Cost Allocation Proposals Approved
The Midwest Independent Transmission System Operator, Inc.’s (Midwest ISO) proposed revisions to its open access transmission and energy markets tariff (TEMT) to incorporate a proposed cost allocation methodology for regionally beneficial projects were conditionally accepted by the Commission effective April 1, 2007. Regionally beneficial projects are economic upgrades that meet specific standards. The Midwest ISO will be required to file annual reports to aid the Commission, the Organization of MISO States (OMS) and stakeholders evaluate the effectiveness of the proposed transmission expansion cost recovery plan and provide the basis for any potential future modifications. In a second order, the Commission addressed the Midwest ISO’s proposed cost allocation methodology for baseline reliability projects rated at 345 kV or above (high voltage) (Midwest Independent Transmission System Operator, Inc., 118 FERC ¶61,208; 61,209).

Natural Gas

Bangor to Pay $1 Million Penalty
A stipulation and consent agreement between the Federal Energy Regulatory Commission’s Office of Enforcement and Bangor Gas Company, LLC (Bangor) resolving certain self-reported violations by Bangor of the Commission’s “shipper-must-have-title” requirement was approved by the Commission. The violations were a result of Bangor’s failure to hold title to the gas it transported on behalf of certain customers. The agreement included a $1 million civil penalty and a compliance plan to assure compliance with the capacity release program and pipeline tariffs, including the “shipper-must-have-title” requirement (In re Bangor Gas Company, LLC, 118 FERC ¶61,186).

Rejection of Pipeline's Force Majeure Cost-Sharing Formula OK'd
The Federal Energy Regulatory Commission (FERC) reasonably rejected a natural gas pipeline company's proposed formula for sharing with shippers the costs of force majeure interruptions—interruptions due to uncontrollable and unexpected factors or events—because it was inconsistent with FERC policy, the U.S. Court of Appeals for the District of Columbia Circuit held. FERC had previously determined that two cost-sharing arrangements—one, a full credit after ten days, and a second, a percentage credit over the entire interruption period—were equitable and that they both incorporated a careful balancing of risk between shippers and pipelines. The pipeline company had effectively cherry-picked the most pipeline-favorable aspects of each formula for its hybrid formula, altering the responsibility for force majeure events in favor of the pipeline and against the shippers. The court also found that FERC reasonably rejected the pipeline company's proposal to include scheduled maintenance as a force majeure event so that shippers would have to share the cost of the associated pipeline interruption. FERC had previously defined force majeure events as events that were not only uncontrollable, but also unexpected. Although some scheduled maintenance interruptions were uncontrollable, the court said, they were not unexpected. (North Baja Pipeline, LLC v. FERC (DCCir) CCH Utilities Law Reports ¶14,637)

Issue of Pipeline's Jurisdictional Status Remanded
The Federal Energy Regulatory Commission (FERC) failed to provide a sufficiently reasoned explanation for why it found that an energy corporation's two pipelines transported natural gas, which subjected them to FERC's jurisdiction under the Natural Gas Act (NGA), as opposed to finding the pipelines performed a gathering function, the U.S. Court of Appeals for the Fifth Circuit ruled. The court said that FERC did not give a reasoned analysis of why it negated the import of factors favoring a determination that Jupiter Energy Corporation's lines served a gathering function in FERC’s application of a multi-factor, primary function test. FERC was required to provide a reasoned analysis for why certain existing, non-jurisdictional indicators were outweighed by the remaining physical factors. Moreover, the court said, FERC did not consider the non-physical factors supporting a gathering function for the pipelines. These could not be ignored when conducting the primary function test: the Fifth Circuit recognized non-physical factors as ``secondary to the physical factors,'' but still required their consideration. (Jupiter Energy Corp. v. FERC (5thCir) CCH Utilities Law Reports ¶14,638)

Oil and Gas Leases

Open, Nondiscriminatory Access in Outer Continental Shelf Proposed
A new process for shippers who believe that they have been denied open and nondiscriminatory access to pipelines on the Outer Continental Shelf has been proposed by the Minerals Management Service. In 2004, the U.S. Court of Appeals for the District of Columbia (Williams Cos. v. FERC) upheld a lower court decision finding that the Outer Continental Shelf Lands Act granted to the Federal Energy Regulatory Commission only limited authority to enforce open-access rules in the OCS, and that a number of FERC’s regulations were invalid. In response, MMS issued an Advance Notice of Proposed Rulemaking asking what regulatory changes it should make to ensure that the OCSLA requirement that pipelines transporting oil or gas on or across the OCS provide open and nondiscriminatory access to both owner and non-owner shippers is met. This proposal builds upon that ANPR and subsequent public meetings.

The new regulations would implement complaint procedures and informal alternative dispute resolution processes. Decisions by the MMS Director would be enforceable by orders to transporters and by civil penalties. The regulations would be applicable to shippers transporting oil and gas from federal leases. MMS would defer to the FERC in the case of pipelines under the jurisdiction of the Natural gas Act or the Interstate Commerce Act, and the regulations would not apply to the pipeline connecting a deepwater port with an OCS pipeline. (CCH Energy Management ¶9310)